Request A Quote!
It Only Takes A Few Seconds
Request A Quote
Business Hours
M-F: 9:00-4:00 ET
75 Aiken Street Unit 100
Charleston, SC 29403
Call Us
843-900-1002

A bank yard is not a compacted yard. Check the shrink and swell factor before you bid.

A cut/fill takeoff tells you how many cubic yards sit in the ground, in place. That number is useful. It is not, by itself, the volume you will haul, or the volume that will land in the fill after compaction. Almost all materials change volume when they move from cut to truck to embankment. If you treat a bank cubic yard as if it were already a compacted cubic yard, import, export, truck counts and haul time all drift — and the miss shows up after award.

Three states of the same material

Federal Highway Administration guidance for Federal Lands highway design is direct on this point. Roadway excavation is typically measured in the original, undisturbed position, and the specifications must clearly state the place and method of measurement, because almost all materials change volume in their movement from cut to fill.

The same FHWA Earthwork Design page walks through the three states estimators actually price:

Excavated solid rock usually goes the other way. Placed in a fill, it typically occupies a larger volume than it did in place. That change is the swell. FHWA notes that when the voids in a rock embankment become filled with earth or other fine material, the volume in the fill will just about equal the combined volumes in the two source locations.

FHWA Federal Lands’ Earthwork Representation Guide uses the same language estimators use on a cut/fill report: shrink/swell factors adjust quantities from the bank (BCY) state to the compacted (CCY) state, and the factors to use are the ones recommended in the geotechnical report. Swell factors (values greater than one) are typically associated with rocky materials. Shrink factors (values less than one) are typically associated with clayey or granular materials.

Do not substitute a rule of thumb for the project factor

FHWA publishes a table of shrinkage and swell values that “may be used for estimating purposes prior to obtaining the project specific information from the Geotechnical Unit.” The same page is explicit about the limits of that table: mass densities are subject to adjustment, a negative swell number represents shrinkage, and the factors are subject to substantial variation. The design, it says, should use data furnished by the geotechnical unit, and when they are available, actual field shrink and swell factors for like material used on adjoining projects.

For ranges, FHWA describes — not prescribes — the following, always dependent on the material and the work:

Those are FHWA’s published ranges for design context. They are not a substitute for the factor in your geotechnical report or the measurement rules in your specification. Shrink, as FHWA notes, can also include slight waste in transport, material that escapes beyond the toe of slopes, and the effect of slightly overbuilt embankments. Settlement of the ground under a new fill can contribute to an apparent shrink, but shrink should not be confused with subsidence of a weak foundation.

If the report is silent, or the spec measures excavation and embankment in different positions (bank versus compacted), that is a bid question, not a gap to fill with a favorite percentage.

Why it belongs in the bid

Once the factor is wrong, several cost centers move at once.

Import and export. If compacted fill takes more bank cubic yards than a 1:1 takeoff assumed, the job can go from “balanced” to short, and you have borrow and haul you did not price. If the material shrinks less than you assumed, or swells, you can end up with waste, a dump site and trucking you did not carry. The takeoff surfaces do not make that adjustment by themselves.

Haul and production. Loose volume is what actually sits in the truck. Understating swell in the haul unit changes cycle times, truck counts and the time on the schedule to move the same bank quantity.

Place of measurement. If the specification measures excavation in the bank and embankment in the compacted position, the shrink/swell factor is how those two numbers meet. If both are measured in the same position, the factor still matters for equipment, moisture and whether on-site material will actually build the fill you planned.

Balance points. FHWA’s Earthwork Design guidance treats shrink and swell as part of balancing cut and fill, including the effect of subexcavation and reserved topsoil. A mass diagram built on unadjusted bank volumes will not match the work you have to perform.

A short pre-bid check

Before you lock import, export and haul:

  1. Confirm how the specification measures excavation and embankment — in the bank, loose, or compacted position.
  2. Find the shrink and swell factors, or the density assumptions, in the geotechnical report and in any design cut-and-fill notes. Note whether they vary by material or by balance.
  3. Compare those factors to your cut, fill, unsuitable, topsoil and borrow quantities. Recast the balance in compacted or pay cubic yards, not only in unadjusted bank yards.
  4. Price the import, export, haul and time those adjusted quantities require. Qualify or clarify the factor if the documents do not give you one you can stand behind.

3 sets of eyes check every project before it reaches your desk.

Complete Bid Proposals. Field Knowledge. Ongoing Support.

If you want another look at the geotech and the grading plan before you bid, send us your plans.

Sources

You send the plans. We build the bid package.

Paydirt provides takeoffs and estimating for excavation and civil contractors across the US. The work is built on field knowledge, not just software: complete excavation estimates grounded in how the work actually gets executed, then support through the bid and after delivery.

This is not a new company introduction. It is a straight account of the services we perform, drawn from what we already publish on paydirtsupport.com.

Takeoffs and estimating

The core of the work is takeoffs and estimating for excavation and civil contractors. That includes:

3D GPS machine control models

When the job calls for it, Paydirt provides 3D GPS models for machine grade control and pipe work, for most GPS brands. The model is there so the field crew can grade to design with a surface that matches the bid, not a separate guess in the cab.

How the work is checked

3 sets of eyes check every project before it reaches your desk.

We serve civil and excavation contractors nationwide — across 40+ states — with the same process wherever the job is. After delivery, we stand behind our numbers and remain available if anything needs to be revisited.

Pricing and turnaround

Every project is quoted from your plans. Typical price ranges and turnaround times are listed in the FAQ on our Takeoffs & Estimating page.

Complete Bid Proposals. Field Knowledge. Ongoing Support.

If you want Paydirt to build the package for your next bid, send us your plans.

Sources for the claims in this article

All service descriptions above are taken from Paydirt’s public site, paydirtsupport.com, including the homepage service list (Takeoffs & Estimating, 3D GPS Modeling) and the statements on three sets of eyes on every project, nationwide coverage across 40+ states, and ongoing support after delivery.

A cut/fill number is only as good as the sheets behind it. Most excavation estimators open the grading plan, glance at the contours, and move on. The misses that blow a bid usually sit in three places people skim: where existing and proposed grades fight each other, where spot elevations and finished floors fight the slopes, and where the margin notes say something the contours don't.

We see the same pattern across excavation bids in 40+ states: solid software output, weak sheet reading. The fix is a short desk check — not another assumption.

Pricing a job now? Send us your plans.

Spot 1: Existing vs. proposed contours

The design grades tell you where the dirt is supposed to end up. The existing contours tell you what is already there. Where those two fight — steep daylight lines, unexplained fill pockets, a pad that sits far above or below the existing surface — your dig and fill story changes.

Check: Trace existing and proposed through the pad, parking and drive areas. Mark every place the difference is larger than the surrounding slope can explain. Those marks are your first cut/fill questions, not afterthoughts.

Spot 2: Spot elevations and finished floors

A finished floor elevation that looks fine in a schedule can still fight the grades around it. When the FFE, the pad elevation and the surrounding slopes don't agree, you inherit undercut, import, retaining or rework you may not have priced.

Check: Pull every spot elevation and FFE that touches the work. Compare each one to the nearest contours and to the sections. If the sheet needs a wall, a bench or a thicker section to make the number work, put it on the clarification list before you lock unit costs.

Spot 3: Margin notes and callouts

Undercut, match existing, temporary stockpile, phase lines, "see civil detail," and "verify in field" notes live in the margins and keynotes. If you only read the contour ballet, you miss the instructions that change stripping, haul and sequencing.

Check: Read the legend, the general notes and every clouded callout on the grading sheets. Copy anything that changes quantity or production onto a one-page checklist next to your takeoff.

A five-minute desk check

Before you trust the software total:

  1. Existing vs. proposed — where do they fight?
  2. Spot elevations / FFE — do they agree with the slopes?
  3. Margin notes — what did the contours not say?
  4. Addenda — did any of those three change after the set you pulled?
  5. Assumptions — write down what the sheets still leave open.

That list will not catch every miss. It catches the ones that show up most often when a bid goes sideways after award.

How Paydirt uses the sheets

With Paydirt, 3 sets of eyes check every project before it reaches your desk — including a pass that is specifically about reading the grading sheets, not just running the model.

Skim less. Check more.

Contours, spot elevations, margin notes. Open all three before you lock the number.

Send us your plans through our work order request form (https://paydirtsupport.com/work-order-request-form/), or call 843-900-1002.

Paydirt: Complete Bid Proposals. Field Knowledge. Ongoing Support.

A takeoff tells you how much dirt. Production costing tells you what it costs to move it. Two contractors can start with the same quantities and end up with very different bids, because the price depends on how the work actually gets done: which machines, how many trucks, how far the haul, how fast the crew can produce. Here’s how to turn quantities into a bid you can win. Pricing a job now? Send us your plans.

1. Quantities aren’t a price

Your takeoff gives you cut, fill, stripping, undercut and import or export. Those numbers matter, but a cubic yard of excavation on one site can cost far more than on another. Access, soils, haul distance and phasing all change the cost of the same yard. Treat the takeoff as the foundation of the estimate, not the estimate itself.

That’s why a bid built by multiplying quantities by a single unit price can miss in both directions. Price too high and you lose the job. Price too low and you win a job that loses money. The goal of excavation production costing is to price the work the way it will actually be built on this site.

2. Haul distance and site balance

Start with where the dirt goes. A balanced site that moves material a short distance is a very different job from one that needs import from offsite or export to a dump. Use the cut and fill balance to plan the mass haul: where you cut, where you fill, and how far material travels. Haul distance drives your fleet size and cycle times, so it shapes the whole production estimate.

Look at haul roads too. Steep grades, soft ground and long routes around obstacles slow trucks down and add cost even when the straight-line distance is short.

3. Equipment selection

The right spread depends on the work. Mass excavation, fine grading, trenching and loading trucks all call for different machines. Match equipment to the quantities and the site conditions, then price each piece for the time it will actually be on the job. Oversizing the spread costs money every hour. Undersizing it slows production and stretches the schedule.

Think about the whole spread working together. Excavators, dozers, compactors and trucks need to be balanced, so one machine isn’t sitting idle waiting on another. Where the job uses 3D GPS machine control, factor in the model and the setup so the field crew can grade to design with fewer stakes and less rework.

4. Crew sizing and production rates

Production rates turn quantities into hours. Estimate how many yards per hour each operation can realistically produce on this site, then size the crew and the fleet to match. Be honest about the conditions: tight access, wet soils or a busy site will slow things down. A production estimate built on realistic rates is what separates a bid that makes money from one that only looks competitive.

Don’t forget the time that isn’t moving dirt: mobilization, setup, weather, testing and waiting on other trades. Those hours still cost money, and they belong in the estimate.

5. Material type and geotech

The geotech report changes how material digs, loads and places. Rock, clay, saturated soils and unsuitable material each affect production, equipment choice and compaction effort. Read the boring logs and recommendations, and build their effects into your rates instead of assuming average conditions.

6. Phasing and access

How the job is sequenced affects cost. Phased construction, limited access points, work around existing buildings or traffic, and erosion control requirements can all force extra moves, smaller equipment or more mobilizations. Walk through the phasing plan and price the job the way it will really be built.

7. Import, export and disposal

Trucking and disposal can be one of the biggest lines in an excavation bid. Price the real cost of hauling: the distance, the number of trucks, dump fees and the cost of approved fill if you need it. Confirm local sources and sites before bid day so the numbers hold up.

Topsoil is part of this too. Decide whether it is stockpiled on site and respread, or hauled off, and price the handling either way.

8. Risk items and clarifications

Every site has unknowns. Unsuitable soils, groundwater, rock and plan conflicts can all change the cost after award. Identify the risks you can see, decide how to price them, and spell out what’s included and excluded in your clarifications. A clear proposal protects your margin and shows the owner you understand the job.

9. From numbers to a complete bid proposal

Bring it together: quantities from the takeoff, production rates, equipment, crew, haul, risk and clarifications, organized into a complete bid proposal. Paydirt builds that package for excavation and civil contractors, with US-based project management and QC on every estimate, backed by our dedicated production team, and 3 sets of eyes on every project before it reaches your desk.

What a strong production estimate shows

When you review an estimate before bid day, you should be able to see the quantities it started from, the production rates it assumes, the equipment and crew it carries, how the haul is priced, and the risks it covers or excludes. If you can’t trace a number back to those pieces, it’s hard to defend on bid day or manage after award.

Ready to turn your takeoff into a bid you can win?

A takeoff number tells you what’s on the plans. A production estimate tells you what it will take to build it. That’s the difference between a number and a bid you can win.

Send us your plans through our work order request form (https://paydirtsupport.com/work-order-request-form/), or call 843-900-1002.

Paydirt: Complete Bid Proposals. Field Knowledge. Ongoing Support.

Paydirt Earthworks Support Services logo
We specialize in using the latest technology and techniques to deliver accurate and reliable results for our clients. Our team of experts is available for travel throughout the USA and internationally to perform our services. Contact us today to learn more about how we can help with your projects.
Copyright © 2026 All Rights Reserved
menu linkedin facebook pinterest youtube rss twitter instagram facebook-blank rss-blank linkedin-blank pinterest youtube twitter instagram