Request A Quote!
It Only Takes A Few Seconds
Request A Quote
Business Hours
M-F: 9:00-4:00 ET
75 Aiken Street Unit 100
Charleston, SC 29403
Call Us
843-900-1002

Latest from Paydirt Support Services

A Bank Yard Is Not a Compacted Yard: Check Shrink and Swell Before You Bid

A Bank Yard Is Not a Compacted Yard: the same material shown in place in the cut, loose in the truck, and compacted in the fill. Illustrative diagram, not to scale.

A bank yard is not a compacted yard. Check the shrink and swell factor before you bid.

A cut/fill takeoff tells you how many cubic yards sit in the ground, in place. That number is useful. It is not, by itself, the volume you will haul, or the volume that will land in the fill after compaction. Almost all materials change volume when they move from cut to truck to embankment. If you treat a bank cubic yard as if it were already a compacted cubic yard, import, export, truck counts and haul time all drift — and the miss shows up after award.

Three states of the same material

Federal Highway Administration guidance for Federal Lands highway design is direct on this point. Roadway excavation is typically measured in the original, undisturbed position, and the specifications must clearly state the place and method of measurement, because almost all materials change volume in their movement from cut to fill.

The same FHWA Earthwork Design page walks through the three states estimators actually price:

  • Bank (in place). The material as it lies in the cut, before it is disturbed. This is the volume a surface-to-surface takeoff reports, and the volume many specifications use for measurement of excavation.
  • Loose (in the truck or stockpile). Once excavated, common material typically occupies more space than it did in the bank. FHWA illustrates the idea this way: 1 cubic yard of earth in the cut may use 1.25 cubic yards of space in the transporting vehicle. That is an illustration, not a factor to copy onto your bid. The actual loose volume depends on the material and how it is loaded.
  • Compacted (in the fill). After the material is placed and compacted to the specified density, common material typically occupies less space than it did in the bank. FHWA’s illustration is that the same 1 cubic yard in the cut may finally occupy only 0.65 to 0.85 cubic yard in the embankment, depending on its original density and the compactive effort applied. The difference between the original volume in a cut and the final volume in a fill is the shrink.

Excavated solid rock usually goes the other way. Placed in a fill, it typically occupies a larger volume than it did in place. That change is the swell. FHWA notes that when the voids in a rock embankment become filled with earth or other fine material, the volume in the fill will just about equal the combined volumes in the two source locations.

FHWA Federal Lands’ Earthwork Representation Guide uses the same language estimators use on a cut/fill report: shrink/swell factors adjust quantities from the bank (BCY) state to the compacted (CCY) state, and the factors to use are the ones recommended in the geotechnical report. Swell factors (values greater than one) are typically associated with rocky materials. Shrink factors (values less than one) are typically associated with clayey or granular materials.

Do not substitute a rule of thumb for the project factor

FHWA publishes a table of shrinkage and swell values that “may be used for estimating purposes prior to obtaining the project specific information from the Geotechnical Unit.” The same page is explicit about the limits of that table: mass densities are subject to adjustment, a negative swell number represents shrinkage, and the factors are subject to substantial variation. The design, it says, should use data furnished by the geotechnical unit, and when they are available, actual field shrink and swell factors for like material used on adjoining projects.

For ranges, FHWA describes — not prescribes — the following, always dependent on the material and the work:

  • For light soil excavation, and for fills constructed on swampy ground subject to settlement, shrink may range from 20 to 40 percent or even greater.
  • For moderate soil excavation, shrink ranges from 10 to 25 percent.
  • For heavy soil excavation with deep cuts and fills, expect a range of approximately 15 percent shrink to 5 percent swell.
  • A swell of 5 to 25 percent is often anticipated in rock excavation, depending on the proportion of solid rock and the size of the rock placed in the fill.

Those are FHWA’s published ranges for design context. They are not a substitute for the factor in your geotechnical report or the measurement rules in your specification. Shrink, as FHWA notes, can also include slight waste in transport, material that escapes beyond the toe of slopes, and the effect of slightly overbuilt embankments. Settlement of the ground under a new fill can contribute to an apparent shrink, but shrink should not be confused with subsidence of a weak foundation.

If the report is silent, or the spec measures excavation and embankment in different positions (bank versus compacted), that is a bid question, not a gap to fill with a favorite percentage.

Why it belongs in the bid

Once the factor is wrong, several cost centers move at once.

Import and export. If compacted fill takes more bank cubic yards than a 1:1 takeoff assumed, the job can go from “balanced” to short, and you have borrow and haul you did not price. If the material shrinks less than you assumed, or swells, you can end up with waste, a dump site and trucking you did not carry. The takeoff surfaces do not make that adjustment by themselves.

Haul and production. Loose volume is what actually sits in the truck. Understating swell in the haul unit changes cycle times, truck counts and the time on the schedule to move the same bank quantity.

Place of measurement. If the specification measures excavation in the bank and embankment in the compacted position, the shrink/swell factor is how those two numbers meet. If both are measured in the same position, the factor still matters for equipment, moisture and whether on-site material will actually build the fill you planned.

Balance points. FHWA’s Earthwork Design guidance treats shrink and swell as part of balancing cut and fill, including the effect of subexcavation and reserved topsoil. A mass diagram built on unadjusted bank volumes will not match the work you have to perform.

A short pre-bid check

Before you lock import, export and haul:

  1. Confirm how the specification measures excavation and embankment — in the bank, loose, or compacted position.
  2. Find the shrink and swell factors, or the density assumptions, in the geotechnical report and in any design cut-and-fill notes. Note whether they vary by material or by balance.
  3. Compare those factors to your cut, fill, unsuitable, topsoil and borrow quantities. Recast the balance in compacted or pay cubic yards, not only in unadjusted bank yards.
  4. Price the import, export, haul and time those adjusted quantities require. Qualify or clarify the factor if the documents do not give you one you can stand behind.

3 sets of eyes check every project before it reaches your desk.

Complete Bid Proposals. Field Knowledge. Ongoing Support.

If you want another look at the geotech and the grading plan before you bid, send us your plans.

Sources

From The Blog

A Bank Yard Is Not a Compacted Yard: Check Shrink and Swell Before You Bid

Material changes volume from the cut to the truck to the fill. Here’s what to check in the geotech and the spec before you lock import, export and haul.

Read More
What Paydirt Does for Excavation Contractors

A clear look at what Paydirt does: takeoffs and estimating, production estimates, complete bid proposals and 3D GPS machine control models — with 3 sets of eyes on every project.

Read More
Why Verifying the Water Table Matters Before You Bid an Excavation Job

A water level recorded on one drilling date is not the same as the high water you’ll dig through. Here’s what to check before you lock the number.

Read More
3 Spots on a Grading Plan Most People Skim

Most cut/fill misses hide in three spots on the grading plan: contours, spot elevations and margin notes. A five-minute desk check before you lock the number.

Read More
Takeoff Number vs. a Bid You Can Win: Why Production Costing Matters

A takeoff tells you how much dirt. Production costing tells you what it costs to move it. Here’s how to turn excavation quantities into a bid you can win.

Read More
Paydirt Earthworks Support Services logo
We specialize in using the latest technology and techniques to deliver accurate and reliable results for our clients. Our team of experts is available for travel throughout the USA and internationally to perform our services. Contact us today to learn more about how we can help with your projects.
Copyright © 2026 All Rights Reserved
menu linkedin facebook pinterest youtube rss twitter instagram facebook-blank rss-blank linkedin-blank pinterest youtube twitter instagram